Nairobi Ring Transmission and Distribution

Transmission Lines and Substations
POWER Engineers, Kenya Electricity Transmission Company
Nairobi, Kenya

PROJECT CATEGORY

Engineer, Procure, Construction Management

PROJECT SUMMARY

The Kenya Electricity Transmission Company (KETRACO), the national transmission system operator of Kenya, commissioned the following:

  • Construction of approximately 100km of a new 400kV double-circuit transmission line from the new Suswa Substation northwest of Nairobi, to the new Isinya Substation to its south;
  • Construction of a new 220kV spur line of approximately 4km to the new Ngong Substation, to the west of Nairobi;
  • Construction of approximately 5km of 220kV underground cable between the expanded Dandora Substation to the new Koma Rock Substation, northeast of Nairobi;
  • Construction of two new 220kV substations at Suswa and Isinya;
  • Construction of three new 220kV / 66kV substations at Koma Rock, Athi River (southeast of Nairobi) and Ngong.

ADM provided comprehensive construction management services to support POWER Engineers in its Owner’s Engineer role on the project.

Above: The Nairobi Ring 400kV transmission line for which ADM provided construction management services